

















 |
|
Plan
Integration Committee (PIC)
The PLCA Long Range Planning Committee, the PLCA Community
Enhancement Project, and the Community Development District-CDD's Beautification
Committee combined to make the Plan Integration Committee.
This was accomplished in an effort to streamline communications and funding for
Pelican Landing community enhancements.
|
|
Committee Members > |
Emory Geller
(PLCA - Finance Committee)

Nelson
Glueck (PLCA -
Unit Owners Committee)
Diane Juneau (Community
Development District)

Dave Osbun (PLCA - Design
Review Committee)

Tom Manuel
(PLCA - Board of
Directors)  |
JUNE 2008 - PIC Update by Tom Manual - PIC
Chairman
The PIC
continues to work toward completing existing plans and commitments
during 2008 and sun-setting by year-end. The Children’s Park is under
construction and should be completed in June. Parking spaces were
removed from the original design due to zoning requirements. Design work
for other projects is complete, although adaptation to meet cost and
permit limitations may be required.
As of late May, we hope to complete one more project for the PLCA—the
renovation of the Canoe Park on Spring Creek, our southern boundary.
Canoeing and kayaking are increasingly popular, logging over 1000
trips/year. The facility needs repair, redesign and reconstruction of
the launching platform, and expansion to accommodate more storage. We
have construction drawings which would accomplish these goals and
greatly enhance the appearance of the area and the enjoyment of
participants. We are revising the scope to meet financial realities and
if necessary will do the project in phases.
The CDD Boards have conceptually approved three projects—the Roll Dock,
additional landscaping at the North Entryway, and the Heron Marsh
Overlook. Design work is complete, and costing and value engineering
are in progress. Pending permit approvals and acceptable costs, these
projects will proceed over the summer or during the early fall.
The Roll Dock is apparently a mystery to some residents. It is located
on Spring Creek, on the traffic circle less than 100 yards to the east
of the Canoe Park and at present may be seen only from the water. In
the early days of Pelican Landing this dock was very popular as a
walking destination. Several years ago deterioration of the dock caused
its closure for safety reasons, and the removal of the boardwalk that
accessed it. The project is to rebuild the boardwalk and dock in its
original footprint, with necessary accommodation to newer requirements,
and with decking lower to the water. Due to shallow water and the
original permits, this dock is not available for motor boats. This
project will renew access to another aspect of the beautiful natural
environment that surrounds Pelican Landing. Parking is available at the
Canoe Park for those who might not want to walk or bike. Together with
the renovated Canoe Park, the Roll Dock will greatly enhance Pelican
Landing’s water access. Pictures of the natural environment may be
found on the web site.
MARCH 2008 - PIC Update by Tom Manual - PIC
Chairman
The PIC has recommended and the PLCA Board has agreed to terminate the
PIC activity in 2008. Although this is not a final report, this is a
good time to review the background, achievements, and remaining plans of
the PIC. In summary, the PIC has been faithful to its original charter
and has added significant value and attractiveness to Pelican Landing,
and thus our property values, although some desirable work is still
incomplete.
The PIC (Plan Integration Committee) was set up in 2004 as a joint task
force between the CDD and PLCA Boards, with the purpose of coming up
with a single, integrated capital improvement plan for Pelican Landing
incorporating the desires and funding of the three Boards (2 CDD and
PLCA). This effort resulted in a five-year, $5 million program, derived
from over $20 million in recommendations developed by the J.R. Lieber (JRL)
landscape architecture firm. This firm had designed much of the
original landscaping of Pelican Landing and authored a Master Plan
received by the boards in 2004.
The original project list approved by the boards in March, 2005 was the
culmination of a multi-year process involving three separate
community-wide surveys, extensive community review, and resident
feedback. Projects were chosen and prioritized based on conceptual
designs and estimates of probable cost developed by JRL. Attention was
given to serving the diverse interests of various groups within the
community, with an overall focus on enhancing its appearance.
The PIC project list and funding were split between the CDDs ($2
million) and the PLCA ($3 million). The PIC had as its primary
remaining responsibility to work with vendors (architects, surveyors,
contractors) to develop details and execute the approved project list.
It was also understood that development and execution of capital
projects is a time-consuming, iterative process involving many
compromises, and that project details, budgets, and even sequence would
need to be adjusted as circumstances required. Although the PIC serves
both the CDD and the PLCA in developing the final plans, ultimate
project authorization is the responsibility of the appropriate Board.
The CDD projects (totaling $2 Million) are funded through an assessment
that appears in the non-ad-valorem portion of your real estate tax
bill. This assessment is $166 per unit per year for four years; the
first installment was levied in Nov. 2007.
The PLCA projects (totaling $3 Million) are funded through the capital
fund derived from past and current property transfer fees ($1500; within
the Colony $1250 goes to PLCA and $250 to the Colony Foundation) and
interest on those funds; this pay-as-you-go method has had and will have
no impact on annual dues or assessment. A commitment was made to use
these fees to rebuild the capital fund after conclusion of the PIC
effort.
After three years of the five-year program authorization, the highest
priority projects and most of the medium priority ones for both the CDDs
and the PLCA have been completed or are substantially complete. As was
anticipated, the specific project details and costs have changed over
the years, but total spending is still well below the authorized
levels. The only project to exceed its original estimates by a
significant amount was the Community Center expansion. The philosophy
has been to do each project in a first-class manner so that we can be
proud of it. Needless to say, the construction environment here has
been turbulent and difficult in a period of hurricanes, materials
shortages, unprecedented boom and bust.
The PIC has followed its original, community-approved charge in the
project selection, as directed by the boards. However the details have
been reviewed and adapted according to input from subcommittees,
interest groups, and concerned residents. Examples of adjustments based
on resident input are:
+
Expansion of the water feature in the Central Entrance Park
+ Adoption of Garden Club recommendations in plantings at the Central
Entrance Park
+ Elimination of planned paver strips in various road locations
+ Elimination of fountain grass and addition of more color in portions
of the entryway landscaping
+ Addition of more color in the canoe park circle.
+ Moving and expansion of the doors between rooms in the Community
Center
+ Addition of a Wi-Fi hot spot in the Community Center
+ Details of the aerobics and fitness rooms in the Community Center
+ Elimination of toilet facilities in the Children’s Park
+ Reconstruction of the Children’s Park in its original location in
place of a proposed Community Park
+ Correction of a pre-existing drainage problem behind Longlake Village
(site of the Children’s Park)
+ Exact routing of the Greenview Drive sidewalk
+ Addition of fencing along the Southbridge perimeter
+ Addition of a storage shed and bleachers/canopies at the Tennis Center
+ Upgrading of the bocce facility
+ Working to meet needs of the Canoe/Kayak Subcommittee at the Canoe
Park (in progress)
The approach to project contracting and construction has differed
between projects. Some are relatively small and can be handled with
only one contractor and skill set, e.g. fencing, sidewalk construction,
installation of plant material. Others are more complex and require
extensive surveying, engineering, and support of the permit process, as
well as the integration of work by various subcontractors, usually by a
general contractor or construction manager. Only qualified contractors
can be used, and such are often in short supply. Multiple bids have
been obtained wherever possible.
The only PLCA project of sufficient magnitude and complexity to need a
general contractor was the Community Center, which utilized a leading
architectural firm, Gora and Associates, and a leading local general
contractor, the Garrett Company. We have engaged Eecon, a general
contractor, for the Children’s Park as well.
The CDD, which follows very strict legal requirements regarding
contracts, was unable to find a qualified general contractor for the
entryways and the Central Entrance Park, despite repeated calls for
bids. Finally work was begun using qualified bidders for components of
the job, with CDD personnel trying to fill the role of the general
contractor. Toward the end of the Central Entrance Park project, we
were able to find a new, qualified firm, Eecon, to serve as a general
contractor. This resulted in acceleration and satisfactory completion
of the project. On all projects involving planting and irrigation, the
CDD has saved residents very significant funds by using CDD personnel
rather than outside contractors.
Completed CDD projects include landscaping (planting and lighting) of
the entryways (the highest priority of residents according to the
surveys and feedback), the Canoe Park circle, and fencing along much of
the community perimeter. Recent progress is highlighted by completion
of the Central Park at the intersection of Pelican Landing Parkway and
Pennyroyal. This features not only a multi-cascade waterfall, but
extensive paver pathways and landscape planting. This project was
completed for slightly less than anticipated in 2004 and fulfills the
original goal of a dramatic centerpiece for Pelican Landing. As a final
touch on the entryways, a monument identifying the gates as Pelican
Landing is under construction at the middle gate.
Engineering is complete and bids have been obtained for the remaining
major CDD project, renovation of the “Roll” Dock on Spring Creek as a
site for nature watching, fishing, and non-combustion-powered boating.
This is a particularly beautiful area which deserves more community
access. The Dock was a popular amenity but was closed to resident
access about 8 years ago, due to deterioration and safety concerns. It
will again be accessed by a boardwalk from the cart path between the
Canoe Park and Bay Creek. Because of its proximity to Pelican’s Nest,
the cooperation of the golf club will be essential. Because of the
difficulty in obtaining permits to make any changes on waterways, our
plan is to reconstruct this dock in the present footprint, although with
much better decking and a closer approach to the water level. At the
last CDD Board meeting, 5 residents spoke in favor of it, and none in
opposition. The Roll Dock project is also supported by the Canoe and
Kayak Subcommittee. As of this writing, it appears that the Bay Creek
CDD alone may fund this. Further fine-tuning of the bids may be
needed. Additional possibilities for CDD funding include enhanced
roadway landscaping.
Completed PLCA projects include expansion of the Community Center,
addition of bocce courts, and addition of a sidewalk along Greenview
Drive. Recent progress includes completion of design, engineering, and
contracting for the Children’s Park, as well as design development for
the Canoe Park (in consultation with the Canoe & Kayak Subcommittee) and
Heron Marsh Overlook.
The Children’s Park is being renovated and upgraded in its original
location on Pennyroyal adjacent to Longlake Village. It replaces a
proposed Community Park including a children’s facility, which would
have been located on Pennyroyal adjacent to Lakemont Cove. An improved
Children’s Park was one of the three major “additional amenity” requests
of the Long Range Plan. The cost of the currently planned Children’s
Park will be approximately that originally estimated for the so-called
Community Park. Contracts have been let and playground equipment
purchased. We are pursuing a Limited Development Order so we may go
forward. Completion now appears likely late this spring.
Funding for the PLCA projects is problematic. Funds on hand ($184K)
will cover construction of the Children’s Park and completion of design
development for the remaining projects. However the real-estate market
slowdown has dried up the source of funds and it appears that we may not
be able to afford additional projects in the near future. In light of
this, the PIC anticipates shutting down in 2008 and archiving the
designs for the uncompleted projects for future use when funding is
available and as future boards may decide. The desirable projects in
the queue include a scenic overlook on Pelican Colony Blvd. between
Sandpiper Isle and renovation of the Canoe Park. These respond to a
major desire of the residents (better viewing of our natural areas) and
to supporting a rapidly growing amenity. Between the Canoe Park and the
Roll Dock renovation, we have an opportunity to add a spectacular
attraction to Pelican Landing in exploiting the beautiful areas along
Spring Creek.
The following tables summarizes approximate PIC spending by project (in
$K). Final audited 2007 numbers are not yet available. Total to date
includes January 2008. Design costs are included. No recent, reliable
costs for the CDD are available.
|
PLCA Project
(* = completed) |
2004-5 Estimate |
Total
To date |
Estimated Final
Total |
Notes |
|
Community
Center* |
1310 |
2000 |
2000 |
|
|
Bocce Courts* |
40 |
51 |
51 |
|
|
Tennis Center* |
100 |
13 |
13 |
|
|
Greenview
Sidewalk |
100 |
108 |
108 |
|
|
Community Park |
200 |
38 |
38 |
Cancelled |
|
Children’s Park |
0 |
78 |
180 |
Contracted |
|
Heron Marsh
Vista |
100 |
19 |
120 |
Designed,
unfunded |
|
Canoe Park/Roll
Dock |
440 |
4 |
220 |
Design in
progress, unfunded: See CDD for Roll Dock |
|
Spring Creek
Park |
415 |
0 |
0 |
No Design,
unfunded |
|
Misc/Contingency |
295 |
11 |
11 |
|
|
TOTAL |
3000 |
2322 |
2703 |
|
|
CDD Project
(* = completed) |
2004-5 Estimate |
Total
To date |
Estimated Final
Total |
Notes |
|
Entryways |
900 |
|
750 |
|
|
Central
Entrance Park |
750 |
|
675 |
|
|
Fencing* |
100 |
|
108 |
|
|
Canoe Park
Circle* |
40 |
|
40 |
|
|
Roadway
Landscaping |
100 |
|
0 |
|
|
Roll Dock |
0 |
|
275 |
Originally PLCA |
|
Contingency/Design Misc. |
110 |
|
230 |
|
|
TOTAL |
2000 |
|
2078 |
|
December 2007 - PIC Update by Tom Manual - PIC
Chairman
The highest priority projects of the PIC—the
entryways and the Community Center—are, as of this writing, either
complete or substantially complete. The medium priority projects—the
Central Park, the Greenview Sidewalk, the Canoe Park Circle, and the
bocce courts—are either complete or well under way. Major delays have
been experienced with the Central Park, but completion is now expected
in January 2008. This project includes not only a signature water
feature, but extensive surrounding landscaping.
As you know, the projects supported by the CDD are funded by a $166/unit
assessment for four years, the first installment of which has already
appeared in your non-ad valorem tax bill. We expect that the CDD will
complete all of its projects (outstanding are the Central Park and the
Roll Dock) in 2008.
There remain three medium priority projects—the Children's Park, the
Canoe Park, and the Heron Point Overlook—to be completed by the PLCA.
As of October, 2007, the PIC has spent about $2.2 million of the $3
million authorized by the PLCA in 2005, so a little less than $800,000
remains for these projects. We believe that sum to be adequate. As
previously stated, a slowdown in real estate sales (which generate
transfer fees that fund our projects) has limited our ability to fund
and pursue these projects, but we have been developing designs and
construction documents to permit rapid construction when funds are
available. We now have enough funds in-hand to move ahead on the
Children's Park and hope to initiate contracts soon. Unfortunately, any
landscaping projects this year or probably next will not reach their
full design appearance until the extreme water shortage eases.
The PIC thanks the residents for their patience and understanding.
September 2007 - PIC Update by Tom Manual - PIC
Chairman
PIC activities have been at a low ebb this
summer, due to absences of key figures all the way from PIC members to
landscape labor. On the PLCA projects, design development and
preliminary cost estimation are continuing, to enable the best use of
our remaining funds. Due to the slowdown in real estate sales, we still
lack enough money to begin any projects. We hope to reach that point in
the fall.
On the CDD projects, replanting at the entryways is underway. Planting
in the canoe park circle is also in progress. The plantings have
suffered severely from weak plant material and insufficient irrigation
due to the drought and watering restrictions. Most of the rock-work at
the water feature is complete, and it should be operational by October.
Additional landscaping in the area will still be required.
June 2007 - PIC Update by Tom Manual - PIC
Chairman
After a prolonged permitting delay, construction began in May on the
water feature at the intersection of Pelican Landing Parkway and
Pennyroyal. This should be substantially complete by fall. The new
entryway plantings were installed in January and February, but due to
the prolonged and unprecedented drought, they have made disappointing
progress. Additionally, some adjustments have been made in response to
resident input. Things should look much better, once the rainy season
has had its effect. The Canoe Park Circle plantings should also be
installed during the rainy season. Bids are being sought at this
writing for the monuments at the South and Central entryways. The CDDs’
funding capability remains intact and their projects should be initiated
and completed on schedule. Costs have been controlled by using CDD
personnel rather than contractors in some cases.
However, funding for the PLCA projects is dependent on revenue from
property transaction fees, which have been severely curtailed as a
result of the real estate slow-down. At present, we do not have enough
funds to initiate any construction. The PIC is developing preliminary
designs and cost estimates for the remaining projects, in order to use
our funds most effectively.
March 2007 - PIC Update by Tom Manual - PIC
Chairman
The expanded Community Center was reopened with a gala event on January
10. The over-all 49% expansion includes a completely new aerobics area
with exercise bar, mirrors and special flooring; two new meeting rooms;
a larger fitness area; new restrooms; a Wi-Fi zone; an expanded patio;
new offices, storage and work area for the staff; and added parking. In
addition, new fitness equipment was added, the building was painted and
re-carpeted, existing structural deficiencies were remedied, and the
entire site was landscaped. Counting the bocce courts, building
renovation, and new and added equipment, your Board has invested over $2
million in the Community Center area over the last 18 months. This is
the centerpiece project of our capital improvement program, and by far
the largest. Response to it is overwhelmingly favorable.
New plantings have been installed at all three entryways to Pelican
Landing. They convey a consistent, attractive appearance consistent
with the original, relaxed, natural “Old Florida” look of the
community. Additional decorative lighting is being installed, as well.
Construction of the water feature in the central park at the
intersection of Pelican Landing Parkway and Pennyroyal awaits permit
actions by Lee County. Addition of fencing by Southbridge and
landscaping of the Canoe Park Circle will begin soon. These projects
are being managed by the Bayside/Bay Creek Community Development
District staff.
At
this point we are past the half-way point in our total $5 million
capital improvement program. Although commitments are not yet firm, the
next major projects will probably be development of a new children’s
park at the Pelican Landing Community Park (on Pennyroyal) and
renovation of the Roll Dock. Both projects are in design stages and not
yet ready for the always prolonged permitting stage.
December 2006 - PIC Update by Tom Manual - PIC
Chairman
At
this writing, the Community Center project is nearing completion.
Interior finishing has begun. Landscaping and irrigation remain to be
completed. Patio lighting is still to be specified. We expect to come
in very near the original budget. We have been delighted with Garrett
Construction’s efforts, quality, and cooperation. We hope to have a
grand opening in mid-January.
Replacement planting at the entryways is in full swing. We are grateful
to Chuck Adams of the CDD for his leadership on this project. When
completed, all entryways will present a refreshed, consistent,
naturalistic look, which fits into the overall landscape themes of
Pelican Landing. Hardscape work (lighting, pavers, etc.) will be
conducted in 2007. The entryway monuments will be modified as the last
item in these areas.
Following entryway completion, the Canoe Park Circle will be improved.
However, since it is a conservation area, our options are limited and it
will remain “native” in appearance.
Contracts have been signed for the water feature in the Central Entrance
Park at Pennyroyal and Pelican Landing parkway. Permitting activities
have begun. Completion by May is planned.
Additional project plans, timing, and budgets are on hold until
financial commitments are fulfilled for the major ones discussed above.
The CDDs will likely proceed with renovation of the Roll Dock in its
original design, thus providing another outlet to Spring Creek.
Initiation of new PLCA-funded projects is dependent on revenue from
house sales, which are currently very low. At present, it appears that
the next PLCA project will probably be the Lakemont Community Park.
September 2006 - PIC Update by Tom Manual - PIC
Chairman
Significant progress
has been made in several areas although the laborious processes of
design, permitting, contract negotiation, and construction continue to
try everyone's patience.
Construction began
in early June on the Community Center expansion. As of this writing
(late August), much of the concrete work is complete and the outlines of
the new areas are clearly visible. Demolition necessary to connect the
new areas with the old has begun, and consequently the only activities
continuing at the Community Center are fitness (18 machines in the old
card room) and administration. Garrett Construction, the architect's
representative, and Nelson Glueck, as our rep, have dealt with many
minor issues that emerged during the start-up. Some adjustments
increased the cost and some decreased it. At present, we are
essentially on budget and on schedule. It is too early to specify a
completion date.
The Greenview
sidewalk has been completed. An additional awning has been added over
the tennis bleachers. A drinking fountain has been added at the Canoe
Park. Final touches will be added to the bocce courts when major
construction nearby is complete. Due to a slow-down in the real estate
transfers that fund the Pelican Landing Community Association projects,
no major new projects will be initiated until 2007.
The Community
Development Districts have authorized funding for their $2M project list
to be paid through an assessment appearing on residents' tax bills
beginning in November 2007. Although agreed and authorized in April,
the contract for the Central Park water feature has not yet been signed
due to bureaucratic delays by the contractor. Work on the water feature
and separate contracts for entryway enhancements should begin this fall.
June 2006 - PIC Update - Tom Manual - PIC
Chairman
The PLCA
has concluded a contract for expansion of the Community Center with D.
Garrett Construction, a leading local contractor, for a guaranteed
maximum price of $1.7 million. This is significantly higher than
earlier estimates, but we are certain it represents the best value
obtainable in today's market. Construction has begun and should be
completed by year-end. Temporary service interruptions in the building
are unavoidable, but these will be minimized and carefully scheduled.
In
addition, a contract has been concluded for construction of a sidewalk
along 90% of Greenview Drive. Due to the topography, some walking in
the street will still be required. Construction has started and should
be completed by late this summer.
Contingent
on approval of final details, the Community Development District (CDD)
Boards have approved negotiation of a contract for $753,000 with Site
Technologies, Inc. to construct the central park and water feature at
Pennyroyal and Pelican Landing Parkway. As in the case of the Community
Center, this project is significantly more costly than anticipated
earlier and other projects' budgets have been changed to accommodate
it. Work on this project should begin in late summer. Additional
projects are scheduled for 2007.
March 2006 - PIC Update - Tom Manual - PIC
Chairman
Tangible results are visible on the one-year anniversary of
authorization of our capital improvement program. The bocce courts are
complete and available for use with seating and shade facilities to
follow. Most of the perimeter fencing additions are complete along the
south berm, at the Community Center, and by the north and south gates.
A storage shed has been completed at the Tennis Center.
Drawings
are complete and out for bidding for the central entrance park with its
water feature, the Community Center expansion, and the Greenview
sidewalk. Due to topographical complications, the Greenview sidewalk
will extend along approximately 90% of the roadway, rather than the
entire route, so some walking in the street will still be required.
The building plans for the Community Center have been approved.
Subsequent changes will need approval that is expected to be routine.
The Development Order request has been re-filed after solution
of several complicated paperwork issues. The committee has worked with
the designer and general contractor to tighten the specifications and
reduce the cost where possible. It should be no surprise to anyone
familiar with the construction scene in our area that the final cost for
this and other major projects will be significantly higher than
originally estimated. To some extent, this was anticipated in our
plans. As stated throughout, we will do a high-quality job on the
highest priority items and as necessary squeeze or defer lower-ranked
ones.
We expect major construction to begin this spring and extend into the
fall. We will minimize disruption to normal activities as much as
possible. The continuing support of residents during this process is
much appreciated.
December 2005 - PIC Update - Tom Manual - PIC
Chairman
The
committee continues to grind through the time-consuming phases of
construction, drawing preparation, contractor selection, permitting, and
bidding. It is evident to all that our costs will be higher and our
timing slower than anticipated, but we expect our budget to be
sufficient to do our higher priority projects fully. It is possible
that later projects may need to be scaled back, but that decision is
many months away. Construction is beginning on the perimeter fencing
additions and the bocce courts. Construction of the Greenview sidewalk
will begin in the first quarter. We expect to have firm costs and
contracts let on the Community Center expansion and the Central Entrance
Park (site of the famous water feature) in the first quarter, with
construction beginning in April 2006, so as to minimize disruption in
season.
September 2005 - PIC Update by Tom Manual - PIC
Chairman
We
continue to progress toward realization of the highest priority community
enhancement projects and a light at the end of the bureaucratic tunnel
that leads to real construction can be seen.
PIC has
filed for a development order including site plans and architectural
drawings for the Community Center expansion. Design work is essentially
complete. We are pleased to have engaged the D. Garrett Co., a leading
area construction company, as construction manager/general contractor.
Cost estimates have shown the expected escalation, but are still within
the anticipated contingency. Construction is expected to begin
immediately after Easter in 2006 and completion is targeted in six months.
Difficulty in locating engineering data has delayed completion of
construction drawings for the entryways and central park water feature,
but hopefully construction can begin this fall with completion in early
2006.
An
agreement has been reached on all details and we are presenting concluding
contracts for the bocce courts, the Greenview sidewalk, and fencing along
the south berm and adjacent to the central and northern entryways.
July 2005 - PIC Update by Tom Manual - PIC
Chairman
We have now received essentially all the internal Board approvals necessary
to proceed with the PIC projects. However, the next stages are painfully
slow, as we proceed through final design, construction documents, engineering,
permitting, contracting, and finally, ground-breaking. Additionally,
spending on the PLCA projects must be consistent with cash flows from property
transfers that are funding it. Any activity connected with construction in
Southwest Florida is characterized by backlogs and delays, so we ask for your
patience during this process.
Our best hope at present is to start work on the central park, the water
feature, and the central entryway by early this fall. The other entryways
should see activity during the late fall and winter. The Greenview
sidewalk, some fencing, and the bocce courts should materialize this fall, as
well. Our target for starting on the Community Center expansion remains
April 1, 2006. Most other projects will begin in late 2006 and early 2007.
Artist's renderings of the entryways and central park, as well as the floor plan
of the expanded Community Center, are on display at the Community Center and at
www.PelicanLanding.com.
For clarification, the PLCA Long Range Planning Committee, the PLCA Community
Enhancement Project, and the Community Development District-CDD's Beautification
Committee combined to make the Plan Integration Committee.
This was accomplished in an effort to streamline communications and funding for
Pelican Landing community enhancements.
April 2005 - PIC Update by Tom Manual - PIC
Chairman
Since obtaining Board approval for the
project list and total budget ($5 million) in February 2005, the PIC and CEC
have been working hard to convert the general plan into specifics and
implement it as rapidly as possible. The committees are working with the
architects to complete development of design concepts. As design for
each project is completed, it moves to preparation of construction
documents, civil engineering, permitting, and finally bidding and
construction. Each of these steps can be lengthy in the very active
Southwest Florida building environment, so we ask everyone to be
patient. The funding mechanism for the PLCA projects is in place and that
for the CDDs' is expected soon.
The first projects to be addressed are
the three entryways and the central entrance park, plus the sidewalk on
Greenview Drive, fencing along the south berm on US 41 and the bocce courts.
The design concept for the central entrance park has been completed.
It contains a 3-tier cascading waterfall feature as well as planting,
paving, and lighting. We hope to begin construction on this area and
the central entryway late this summer.
Although expansion of the Community
Center is a top priority item, we are targeting the initiation of
construction for April 2006. The time required for the remaining
pre-construction process would have let us begin construction late next fall
but required partial shut-down of the current building during the height of
the winter season, so we elected to delay. This has allowed us to
address some lower priority projects sooner.
Bearing in mind that the true cost of
any project will not be known until contracts are let, the current major
project list is below (contingency and minor options not shown). The
exact schedule depends on many factors and cannot be specified at present.
|
PLCA Projects
(Budget) |
CDD Projects
(Budget) |
| |
|
|
Community Center Expansion ($1,310K) |
Central Entryway ($400K) |
|
Heron Marsh Vista ($100K) |
Central Entrance Park ($600K) |
|
Canoe Park/Roll Dock ($440K) |
North Entryway ($300K) |
|
Tennis Landscaping ($70K) |
South Entryway ($315K) |
|
Lakemont Family Park ($200K) |
Canoe Park Circle ($40K) |
|
Spring Creek Park ($415K) |
Fencing ($100K) |
|
Bocce Courts ($40K) |
|
|
Greenview Sidewalk ($100K) |
|
February 2005 - Community Investment Plan
On February 16, 2005, the combined
Boards of the PLCA, Bayside CDD and Bay Creek CDD approved proceeding with
the revised Community Investment Plan proposed by the
Plan
Integration Committee. The sequence of projects and the
proposed funding for specific projects have changed. In addition,
the proposed pathway by the Reserve extending into Heron Marsh South has
been deleted, and enhanced Tennis Center landscaping has been added.
Many changes suggested by residents have been recommended to the
architects. As previously noted, the designs are still incomplete,
so design details and project costs are subject to further change.
Residents will be informed of the final designs and costs when they become
available. The approved project is for the original amount
presented.
Resolution Adopted (2/16/05) by Boards of PLCA,
Bay Creek CDD and Bayside CDD
Resolved:
This Board (PLCA, Bayside CDD, or Bay Creek CDD) herewith
approves the expenditure of $5 million within the next 5 years for community
enhancement and capital improvements on behalf of the residents of Pelican
Landing, as detailed below:
Of the $5 million, $3 million will be to the account of PLCA
and $2 million to the account of the Community Development Districts.
The PLCA portion will be funded from interest income to the
Capital Fund and contributions to it. The Capital Fund may be drawn down
below $2 million in the short term to bridge funding gaps, but will be returned
to the $2 million level by the end of the 5-year period; such draw-downs will be
kept to the minimum possible.
The CDD portion will be funded by resident assessment as
determined by CDD Boards.
The attached project list and priority sequence (Attachment A)
is approved as follows.
a. Project costs at this time are understood to be approximate
and may change as detailed designs are developed and contracts are awarded.
b. Regardless of changes in individual project
costs, the total funds expended will not exceed $5 million.
c. If approved projects cost less then the
present estimates, any "excess" funds will be available for lower priority
projects.
d. Projects should be advanced as rapidly as
practical within the constraints of funding permitting, and prudent management.
Best practices, including use of construction managers
and competitive bidding, will be applied to control costs.
The attorneys and staffs of the PLCA and Community
Development Districts are directed to cooperate to the fullest in
facilitating the accomplishment of all projects.
The Community Enhancement Committee (CEC) and Project
Integration Committee (PIC) will continue to work together with the
architects to complete detailed designs.
The PIC will report monthly to the UOC and to the Boards
on progress in design and contracting.
Before execution, any contract will be approved by the
Board(s) (PLCA or CDDs) paying for it.
The "landscape palette" (plant selection guide)
contained in the Landscape Master Plan Part I is hereby adopted and should
be used as a guide for maintenance, replacement, and upgrading that occur
during the course of normal operations.
|
Project |
Budget $K |
PLCA |
CDD |
Start |
|
Center Entryway |
400 |
|
400 |
2005 |
|
North Entryway |
300 |
|
300 |
2005 |
Central Entrance Park
(Pennyroyal/PL Parkway) |
525 |
|
525 |
2005 |
|
Community Center (bldg) |
950 |
950 |
|
2005 |
|
Bocce Courts |
40 |
40 |
|
2005 |
|
Community Center Landscaping |
360 |
| |